7.5 Phased
PHASED:
Setup costing by CostCenter, by Phased and by Group Product
Step 1: Create Costcenter and setup allocate expense.
From Main Menu choose General Setting Information, CostID:

CostCenter ID
CostCenter Name
Cost Group: 621 : Raw material, 622: Labour cost and 627: Overhead cost.
Setup allocate expense:
PhaseID: set up expense for each phase. Phased should be 1,2,3,etc… or All (All of phase)
CostMethodID: is method allocate expense for each group product, product
Option 1 : allocate direct material
Option 2 : allocate by rate
Option 3 : allocate by customize
Step 2: Setup rate allocate expense for each phase.
Firstly, expense after summary in period will be allocated for each phased.
AllocationPhaseID: Default is option 1 (use for all CostCenterID)
PhaseID: phase No.
Rate: rate for each PhaseID
FromDate -ToDate: Time to apply

Step 3: Setup rate for each Group Product
Applied when allocate expense by quantity multiplication rate (CostMethodID = 2, AllocationMethodID = 1).
Firstly, expense after summary will be allocate for each phase, second will be allocate for each group.
Setup:
GroupID:
Rate: If evenly distributed by quantity should be choose 1 for all GroupID
PhaseID
FromDate -ToDate: Time to apply

Step 4: Setup rate for each product
Applied when allocate expense by quantity multiplication rate (CostMethodID = 2, AllocationMethodID = 1). Firstly, expense after summary will be allocate for each phase, second will be allocate for each group, third will be allocate for each product
Setup:
ProductID
Rate: rate by Coefficient, Selling price or Simple method.
PhaseID
FromDate -ToDate: Time to apply

Last updated
Was this helpful?